Sogin has started with the dismantling of the nuclear power plant in Latina
Sogin SpA (Societa Gestione Impianti Nucleari) has officially started demolishing the screens of the steam generators of the reactor at the power plant of Latina. The screens are the reinforced concrete structures that insulated the upper conduits connecting the six boilers to the reactor building from the outside. About 93% of the conventional material used for the plant construction will be recovered with the decommissioning, 93%. The decommissioning will be completed by January 2021 and will produce a total of about 1,200 tons of material that will be sent to recovery.